POWER / OPPORTUNITY AND CONDITIONS

Energy for new possibilities

The planned substation nearby is a reason to look ahead. Available capacity for our site must first be confirmed by the grid operator.

Plan
110/22 kV

TR Dvory · ČEZ Distribuce

Source
Plan
2029–2030

Planned substation delivery

Source
Plan
80–100 MW

Power for the strategic park, not our site

Source

Connection is unconfirmed. Proximity to the substation does not create a right to capacity. We do not have a documented ČEZ Distribuce connection statement or confirmed reserved capacity.

What the grid plan includes

ČEZ Distribuce’s draft development plan from March 2026 includes the new Cheb (Dvory) substation. The neighbouring park’s documentation describes a 110 kV loop from line V1283 and an underground connection to the park.

Plan owner: ČEZ Distribuce. Document: PRDS 2026–2035, draft 03/2026, table 8.6.

Fact

Baseline capacity in the area

SubstationFree capacity
Jindřichov3 MVA
Drmoul11 MVA
Aš25 MVA
Vítkov15 MVA

Historical baseline at the end of 2025, PRDS table 5.10. This is not a current connection offer.

Source

From proximity to connection

  1. Define demand

    Establish capacity, load profile, resilience and phasing for each option.

  2. Request a connection statement

    Submission is not confirmed in the available records. Capacity, conditions and timing must be established.

  3. Assess technical feasibility

    Connection study, independent supplies and fibre availability according to investor requirements.

  4. Agree the conditions

    Only specific contractual and technical conditions can turn a vision into an investment ready for delivery.

Sources and context4

Based on sources recorded as of 17 October 2026. Future milestones are plans of their respective owners, not delivery guarantees.