Connection is unconfirmed. Proximity to the substation does not create a right to capacity. We do not have a documented ČEZ Distribuce connection statement or confirmed reserved capacity.
What the grid plan includes
ČEZ Distribuce’s draft development plan from March 2026 includes the new Cheb (Dvory) substation. The neighbouring park’s documentation describes a 110 kV loop from line V1283 and an underground connection to the park.
Plan owner: ČEZ Distribuce. Document: PRDS 2026–2035, draft 03/2026, table 8.6.
Baseline capacity in the area
| Substation | Free capacity |
|---|---|
| Jindřichov | 3 MVA |
| Drmoul | 11 MVA |
| Aš | 25 MVA |
| Vítkov | 15 MVA |
Historical baseline at the end of 2025, PRDS table 5.10. This is not a current connection offer.
SourceFrom proximity to connection
Define demand
Establish capacity, load profile, resilience and phasing for each option.
Request a connection statement
Submission is not confirmed in the available records. Capacity, conditions and timing must be established.
Assess technical feasibility
Connection study, independent supplies and fibre availability according to investor requirements.
Agree the conditions
Only specific contractual and technical conditions can turn a vision into an investment ready for delivery.
Sources and context4
- Plán rozvoje distribuční soustavy 2026–2035
- EIA MZP539 Mercedes-Benz Truck Park v Chebu (dokumentace PDF 8,5 MB, přílohy 85 MB)
- Studie proveditelnosti SPP Cheb — manažerské shrnutí
- žádost o připojení VN/VVN, lhůta 30 dnů
Based on sources recorded as of 17 October 2026. Future milestones are plans of their respective owners, not delivery guarantees.